Airport Moves Forward on Terminal, saves $10 mil

The Panama City – Bay County International Airport Authority has approved the design and construction of the terminal building at its new airport now under construction in West Bay.

The new terminal design includes several improvements and cost saving measures planned to keep the project on budget.

At the request of the Airport Authority Board, the general contractor, Walbridge, worked with the airport’s architect (HNTB), engineer (PBS&J) and construction manager (KBR) to identify cost savings in order to bring the cost of the terminal building within budget.

Through value-engineering, the construction team was successful in lowering the cost by $9.8 million to $58.8 million.

The new terminal will be 125,000 square feet and have 7 gates. The airport aims to have the first LEED certified Terminal Building in the nation, with a state-of-the art storm water management system, extensive use of sustainable materials and a landscaping plan that will not require supplemental irrigation.

“From the beginning of this project we have been focused on two things.  First, we want to build a world-class facility capable of serving our region for decades to come with more flights and lower fares.  And second, we are closely managing this project to ensure our community gets the best value for every dollar we spend,” said Joe Tannehill, Airport Authority chairman.

“We challenged the decision team to identify cost savings while improving the overall design of the terminal.  I’m proud to say they delivered,” said Tannehill.

Last month, the Airport Authority announced its intentions to construct a 10,000-foot main runway, subject to obtaining necessary permits and approvals. The Authority also had approved a thicker runway and centerline lighting to accommodate a 10,000 foot runway.

Construction of the $318 million state-of-the-art airport began in January 2008 and is now nearly three months ahead of schedule. The runway has been graded and paving is scheduled to begin in early October, four months ahead of schedule.

The new commercial airport, the first built in the United States since the mid-1990s, is scheduled to open in May 2010.

Runway Paving Started at New Airport

Construction of the airport continues to proceed several months ahead of schedule with nearly 45% of the heavy civil construction portion of the job complete with only 35% of the time used.

The project is still about 3 months ahead of schedule.

There are currently 203 workers and 138 pieces of equipment on site.

  • Asphalt paving on Taxiway D is started on Monday, October 6, 2008.
  • Asphalt paving on the north end of Runway 34-16 is expected to begin on Thursday, October 9, 2008.
  • The earthwork in the General Aviation area is 99% complete.

The utility package for the airport property will be finished and released the beginning of the week of October 13, 2008.

The mandatory pre-bid meeting for the utility package is scheduled for Wednesday, October 15, at 1:00 p.m. at the current airport. Bid packages are due to the Airport Authority Office by Friday, October 31, at 1:00 p.m.

New Airport Runway Deeper, but Not Longer – yet.

In a somewhat boring meeting that was exciting at the same time, the Airport Authority unanimously accepted the lowest bid for the terminal, with the stipulation that they needed to come back $4 to $6 million less than where they were at.  If that confuses you, let me clarify, because it was confusing to me at first.

The bid for construction was awarded to Walbridge, who was the low bidder at $68 million.  The Airport Authority had determined a budget of $54 million for the terminal based on preliminary studies and had confirmed this as recently as May of this year.  Former Panama City Mayor Gerry Clemons pointedly asked what changed between May and now to cause an increase of $14 million and after not being answered once, he asked again.  Again David Hanson of Walbridge danced around and avoided the question.  The gracious Joe Tannehill eloquently stated “we are where we are”, indicating he was ready to move on from that particular merry-go-round.  Mr. Tannehill asked Hanson and a representative from HNTB, the architecture firm, whether they had been in communication and working together to come up with the best solution to cut costs without effecting the overall usability, quality, and public appearance of the new airport terminal.  The answer was a quick no, only not said in so few words.  Again, Mr. Tannehill so eloquently stated that if they didn’t come together, they would be both looking for work as the airport job wouldn’t be a job their firms would have any longer. The two firms assured the board that they would have a presentation in a week specifying the approach that would lower the costs an additional $4 to $6 million and they would have a suitable, acceptable contract for the bid on or before October 7th.  Wow, say that out loud – what a mouthful.

Mr. Jeff Dealy, in his construction update, announced that currently, test strips were being laid down for the runway.

The Board unanimously approved increasing the runway depth to 15 inches with the top layer consisting of concrete.  It was discussed lightly the need to go ahead and construct the entire 10,000 feet of the runway, which is an extension of the initial 8,400 feet.  This was not voted on as they are still awaiting permitting from the FAA for the extension, and they didn’t want to “get ahead of the FAA”.  This will be formally decided upon the meeting after the permitting is approved.  Centerline lighting on the runway was also approved.

During the public participation portion of the meeting John Caylor, candidate for County Clerk and zaney “investigative reporter” tried to get in some hoopla about how the public showed they did not want the airport through vote and proceeded to talk about how St. Joe was a bunch of crooks.  John, throwing the vote on a Democratic ballot and seeing a 22% voter turnout with 54% of overall turnout voting against the airport is hardly overwhelming.  After a quite boistrous performance, he was told to leave by the Airport Cheif of Police.

Officials Want New Airport to be "aerotropolis"

As reported by emeraldcoast.com:

Panama City-Bay County International Airport officials want the new $330 million facility to be an “aerotropolis” that draws international flights and business to West Bay.

To meet that goal, airport leaders are in discussions with several international carriers and have hired John Kasarda, a scholar, author and the man who coined the term “aerotropolis.”

Airport Executive Director Randy Curtis said airport officials are in talks with several airlines in Canada and England. He described the discussions as ongoing but declined to name the airlines.

Bill Cramer, the vice chairman of the Airport Authority, confirmed the discussions but also declined to name names.

“They’re not willing to go on the record,” Cramer said of the airlines.

However, he added the airport’s new hire will be instrumental in bringing in those international flights and other businesses.

Continue reading “Officials Want New Airport to be "aerotropolis"”

Jerry Ray Discusses New Airport on HomeAwayPodcast.com

Jerry Ray, the Senior Vice President for Strategic Alliances for the St. Joe Company, was interviewed this week on the HomeAwayPodcast site. The topic of discussion was the new airport and what it is going to do for our area.

Jerry starts by giving an account of the history of St. Joe and where it all began. He continues by giving the history of the airport relocation project, how it all started and discusses the process it has gone through thus far.

You can listen to it by downloading it, or listen to it online.

Construction Update – New Panama City Bay County International Airport

Panama City Airport Aerial

Huge progress has been made since construction began at the beginning of the year at the new Panama City Bay County International Airport site north of up Highway 79 north of Highway 388 in Bay County.

The entire site consists of 4,000 acres that can be used for the airport and all future expansions with a total 1,300 acres permitted for construction right now. Phase I will include a primary runway of 8,400 feet and a secondary cross-wind runway of 5,000 feet. The primary runway will run almost due north at 340 degrees with the secondary at around 50 degrees.

Continue reading “Construction Update – New Panama City Bay County International Airport”