Runway Paving Started at New Airport

Construction of the airport continues to proceed several months ahead of schedule with nearly 45% of the heavy civil construction portion of the job complete with only 35% of the time used.

The project is still about 3 months ahead of schedule.

There are currently 203 workers and 138 pieces of equipment on site.

  • Asphalt paving on Taxiway D is started on Monday, October 6, 2008.
  • Asphalt paving on the north end of Runway 34-16 is expected to begin on Thursday, October 9, 2008.
  • The earthwork in the General Aviation area is 99% complete.

The utility package for the airport property will be finished and released the beginning of the week of October 13, 2008.

The mandatory pre-bid meeting for the utility package is scheduled for Wednesday, October 15, at 1:00 p.m. at the current airport. Bid packages are due to the Airport Authority Office by Friday, October 31, at 1:00 p.m.